€180m N7 Newlands Cross & N11 Arklow Rathnew PPP Scheme

  The N11 Arklow/Rathnew, Arklow

Project ID 128978
Date Updated 19/11/2014
County Co. Wicklow
Value €180,000,000

Project description

On the 18th of November 2014, the N7 overpass at Newlands Cross was officially opened 3 months ahead of schedule.

BAM Building Limited are currently undertaking construction work on the N7 Newlands Cross & N11 Arklow Rathnew PPP scheme. The scheme consists of the following elements;

- The design, construction, operation, maintenance and financing of approximately 16.5 kilometres of dual carriageway linking the existing Arklow Bypass with the existing Rathnew/Ashford Bypass in Co. Wicklow, together with several kilometres of associated side roads and link roads.

- The design, construction and financing of the upgrading of the existing Newlands Cross N7 Naas Road / R113 Belgard/Fonthill Road at-grade junction to a grade-separated junction, resulting in the creation of an N7 overpass.

- The design, construction, operation, maintenance and financing of the N11 Gorey North Service Area.

- An additional 31km section of the existing N11 route (Arklow Bypass and Arklow-Gorey Bypass) will also form part of the Project Road and will be operated and maintained by the PPP Concession Co.

All such elements of work set out above are approximate only and may be reduced or added to by the Authority following dialogue with those Candidates selected to proceed to the next stage of the competition or otherwise at the Authority's absolute discretion. The Authority may also extend the operation and maintenance elements to include other parts of the national road network.

Construction work on the overall scheme is expected to be complete by Q4 2015. The break down of the schedules of these works is as follows;

N11 Arklow / Rathnew dual carriageway - Autumn 2015
Upgrade works to existing N11 - Summer 2014
Gorey Service Area and Interchange - Winter 2014

BAM Contractors, formerly Ascon have been operating in Ireland for 57 years. It is a wholly owned subsidiary of the Royal BAM Group of the Netherlands. BAM Contractors covers the entire spectrum of construction in Ireland. BAM Building have also been entrusted with the construction and operation of eight new primary and secondary schools across Ireland as part of a PPP Contract; these are scheduled for opening in September 2014. These Irish successes for BAM are mirrored across Europe with over 30 operating concessions in sectors such as roads, schools, healthcare, prisons and rail.

Companies

Promoter

National Roads Authority

Contact
Mr. Kieran Kelly
Address
St. Martin's House, Waterloo Road
Phone
Fax
+35316680009
Email
Website
Agent

National Roads Authority

Contact
Mr. Kieran Kelly
Address
St. Martin's House, Waterloo Road
Phone
Fax
+35316680009
Email
Website
Main Contractor

BAM Building Limited

Contact
Mr. Darren Devane
Address
Head Office, Kill
Phone
Fax
+35345877264

Categories

Sector Category
Civil and Utilities Transport (Roads & Bridges)

Project History

20/11/2014
Description was updated
19/11/2014
Description was updated
21/11/2013
Description was updated
06/06/2013
Contract Stage updated to On Site
06/06/2013
Start Date updated to 06/06/2013
30/04/2013
Contract Stage updated to Contract Awarded
30/04/2013
Start Date updated to 03/06/2013
30/04/2013
End Date updated to 03/10/2015
30/04/2013
Project Roles were updated
30/04/2013
BAM Contractors have been appointed to carry out work on this development.
22/01/2013
Contract Stage updated to 200
22/01/2013
Start Date updated to 01/07/2013
22/01/2013
End Date updated to 01/07/2015
22/01/2013
Project Roles were updated
13/11/2012
Start Date updated to 02/04/2013
13/11/2012
Finish Date updated to 02/04/2015
13/11/2012
Project Roles were updated
12/10/2012
Start Date updated from 10/10/2012
12/10/2012
Finish Date updated from 10/10/2014
24/05/2012
Start Date updated to 10/10/2012
24/05/2012
End Date updated to 10/10/2014
21/12/2011
Start Date updated to 01/06/2012
21/12/2011
Finish Date updated to 01/06/2014
11/11/2011
Start Date updated from 01/09/2011
11/11/2011
Finish Date updated from 01/09/2013
11/11/2011
It is envisaged that the project will progress through a Public Private Partnership (PPP) initiative.
11/11/2011
The project has been included in the Governments Infrastructure & Capital Investment Programme 2012-2016.
08/07/2011
Contract Stage updated to Contract Awarded
08/07/2011
Project Roles were updated
08/07/2011
Funding is expected to be sought in late Summer 2011.
08/07/2011
The contract is expected to be officially awarded once full funding has been secured for the project.
08/07/2011
BAM PPP and Balfour Beatty Capital Limited have been identified as the successful tenderer for the project.
13/05/2011
Funding Type updated to Public
13/05/2011
Start Date updated to 01/09/2011
13/05/2011
End Date updated to 01/09/2013
13/05/2011
Construction work is expected to commence in Q3/Q4 2011.
13/05/2011
A main contractor is expected to be appointed in Q2/Q3 2011.
04/05/2011
Start Date updated to 09/05/2011
11/04/2011
Construction Type updated to Civil Works
11/04/2011
Description was updated
03/02/2011
The preferred bidder for the scheme is expected to be announced in April 2011.
25/01/2011
This project has secured funding from the Department of Transport, see attached news item
02/12/2010
Start Date updated to 03/05/2011
02/12/2010
End Date updated to 03/05/2013
02/12/2010
Construction work is expected to commence in Q1/Q2 2011.
08/10/2010
Project Categories were updated
12/07/2010
Planning Stage updated to Planning Not Required
12/07/2010
12/07/2010 - We understand a shortlist of two contractors has been completed.
12/07/2010
18/02/2010 - Cost obtained.